How to update Strategy achievement and Tactic implementation status?

  1. Right click on node for which you have to update Tactic implementation status. Click on “Tactic Planning”.
  2. Update the Status for each node’s tactic. Status can be Not Started (NS), In Progress (IP), Freeze (F) or Complete (C).
  3. On the left-hand menu, open S&T Execution and click S&T Execution Status. S&T tree will show the “buffer status” as a color code for the status of each Strategy and Tactic.
  • 1. Right click on node for which you have to update Tactic implementation status. Click on "Tactic Planning".
Your S&T tree now becomes a Dashboard showing the “buffer status” as a color code for the status of each Strategy and Tactic. The letter in the upper right corner denotes the status (C= Complete, IP = In Progress, F= Freeze and NS= Not Started) The colors indicate if the node is being achieved in the planned timeframe (green) or is in a warning zone (Red or Yellow) or overdue (Grey). “Freeze” (Dark Blue) is a change is frozen to stop bad multi-tasking